|
Patuxent
Park
Revitalization Project
|
 Phase
One of this project began in July 2009 and will include the
reconstruction of roads, sidewalks, storm drainage,
stormwater management and water/sewer lines for Midway Drive
(from MD 246 to Bunker Hill Drive), Gambier Place, Princeton
Drive and Bunker Hill Drive. Construction of Phase 1 is
scheduled to take 10 months.
If you have any questions,
please contact the DPW&T Project Manager, Allen Settle, at
301-863-8400, ext. 3525 or the METCOM Project Manager,
Steve Engleson, at 301-373-4733, ext. 307 (7:00am to
4:30pm); or Standby Service at 240-538-8576 (4:30pm to 9:00pm);
or Emergency Service at 301-373-5305 (9:00 pm to 7:00 am). This
monthly Construction Update was prepared by the St. Mary’s
County DPW&T, the St. Mary’s County Metropolitan Commission and
Gradient Construction, LLC.
|
|
Documents for
Download
Offered in PDF
format
|
|
|
|
Patuxent Park Revitalization Project - Phase 1
Construction Update for February 2010
|
Work
hours are from 6am to 8 pm, Monday thru Saturday for Midway Drive,
Princeton Drive, and Gambier Place; and 6 am to 4 pm, Monday thru Friday
for Bunker Hill Drive. No Parking” signs will be posted 2 days prior to
work beginning on each street. All work is weather permitting.
 Midway
Drive (from MD 246
to
Bunker Hill Drive)
Removal of the existing curb
and gutter and installation of new curb and
gutter will begin the second week of the
month. Removal of the existing asphalt
roadway, excavation of the roadway to
subgrade, and installation of new gravel
base material and base asphalt will occur
during the third and fourth weeks of the
month. Work during the end of the month
may include the removal and installation of
concrete sidewalks and driveway entrances
depending on completion of the above. Work
will require the closure of one lane of
traffic during the daytime as needed.
Residents are requested to find an alternate
location for parking when work occurs on
their side of the street.

Gambier
Place (from
Midway Drive to the
end of Cul-de-sac)
No work is scheduled for this month.
Princeton Drive
(from
Midway Drive to the
end of T-Turnaround)
Installation of the sanitary sewer line and
house connections should be completed by the
end of the first week of the month. Work
will require the closure of one lane of
traffic during the daytime.

Bunker Hill Drive
(from
Midway Drive to
Nicolet Park
entrance)
Storm drain installation will be performed during the first week of the
month. Work will require the closure of one lane of traffic during the
daytime as needed.
Please be aware of
construction vehicles entering and leaving the stockpile/staging area.
|